DC procurement data

A copy of the records on contracts.ocp.dc.gov, the website where DC's Office of Contracting and Procurement publishes contracts, purchase orders and payments, as we pulled them. About this source. Not a complete record of District contracting or spending.

How the District buys things

The rules behind the records on this site, for people new to DC procurement, with software and IT purchases in mind. Each rule links to its law or regulation; quoted words are the source's own.

Every source was read on 12 October 2026: D.C. Code on code.dccouncil.gov, regulations (DCMR) on dcregs.dc.gov. Each claim, its source and the quoted text are listed in how_dc_buys_sources.md.

The dollar lines

Where the rules change. Each row links to the section below that gives the source.

AmountAppliesWhat the law requiresDetails
$10,000or lessA contracting officer may buy without competitive quotes.How a contract gets awarded
$25,000overIT purchases by agencies under the Mayor go to OCTO for review. One OCTO hasn't reviewed "shall be deemed recommended for disapproval to the Chief Procurement Officer".Technology purchases and OCTO
$100,000or lessSmall purchase: at least three written quotes above $10,000. A purchase may not be split to stay under $100,000.How a contract gets awarded
$100,000overCompetitive sealed bidding, unless the CPO issues a determination and findings (D&F) for another method.How a contract gets awarded
$100,000or moreThe contract goes in the portal's contract database, with the executed contract, all D&Fs and all modifications.What the portal has to publish
$250,000or lessSet aside for small business enterprises (SBEs).Small and local business rules
$250,000overOn non-construction government-assisted projects, at least 35% of the dollar volume subcontracted to SBEs, unless waived.Small and local business rules
$1,000,000over, in a 12-month periodThe Council must approve the contract, and each option year over the line goes back to the Council.When the Council must approve

Who does the buying

The main law is the Procurement Practices Reform Act of 2010, D.C. Code § 2-351.01 and following. It sets up the Office of Contracting and Procurement (OCP), an independent agency run by the Chief Procurement Officer (CPO). Through the CPO, OCP has exclusive authority to administer the law, except where the law provides otherwise.

Exact wording: D.C. Code § 2-352.01(a)(1)
"There is established as an independent agency the Office of Contracting and Procurement, which shall be administered by the Chief Procurement Officer. Except as otherwise provided in this chapter, OCP, through the CPO, shall have the exclusive authority to administer the provisions of this chapter." D.C. Code § 2-352.01(a)(1)
  • The CPO may delegate contracting authority to agency employees ("The CPO may delegate contracting authority to employees of an agency"), and the agency decides what it needs and runs the contract once awarded (§ 2-352.01(a)(4)–(5)). OCP describes itself as managing "the purchase of $5.7 billion in goods, services and construction annually, on behalf of over 79 District agencies" (About OCP; the page gives no date for that figure).
  • Some agencies follow the same law but buy on their own, outside the CPO's authority. The statute names, among others, the Chief Financial Officer, the Attorney General, UDC, the Housing Authority, the Public Library, DC Public Schools, the Child and Family Services Agency and the Department of General Services (§ 2-352.01(b)). DGS buys construction, facilities maintenance, real estate, utility and security services (§ 2-352.01(d)).
  • Some bodies are outside the procurement law altogether, including the courts, the Public Defender Service, DC Water, the Washington Convention and Sports Authority, and grants and loans (§ 2-351.05(c)). The Council runs its own buying (§ 2-351.05(b)).
  • The portal keeps its own list, Independent Agencies. It doesn't match the statute's lists exactly (it includes Lottery and Charitable Games, for example, which § 2-352.01(b) does not name), so check both.

Contracts by agencies outside OCP may be missing from the portal or only partly there. See About this source.

Technology purchases and OCTO

The statute for the Office of the Chief Technology Officer (OCTO) tells it to review and approve all agency proposals, purchase orders and contracts for information technology and telecommunications, and to recommend approval or disapproval to the CPO.

Exact wording: D.C. Code § 1-1403(2)
"Review and approve all agency proposals, purchase orders, and contracts for the acquisition of information technology and telecommunications systems, resources, and services, and recommend approval or disapproval to the Chief Procurement Officer" D.C. Code § 1-1403(2)
  • The $25,000 line. A regulation applies this to IT purchases "valued over $ 25,000", and anything over that amount OCTO hasn't reviewed "shall be deemed recommended for disapproval to the Chief Procurement Officer" (1 DCMR § 5602). That chapter "applies to all subordinate agencies" (1 DCMR § 5600).
  • What counts as IT is broad: it includes "all technology services provided by vendors or contractors" and "all costs associated with developing, purchasing, licensing or maintaining software" (1 DCMR § 5601).
  • OCTO is also to "Issue regulations governing the acquisition, use, and management of information technology" and "Review and approve the information technology and telecommunications budgets" of agencies (§ 1-1403(1), (3)).
  • OCTO's own policy says IT projects "must be approved by the District Chief Technology Officer (CTO) before money can be spent", and that OCP issues purchase orders and contracts "only after the required CTO approval is obtained" (IT Procurement and IT Project Policy, approved February 2021, reviewed May 2024).
  • DC's Inspector General found in April 2019 that the review depended on the commodity code an agency picked: OCTO's automated controls "allowed other District agencies to select non-ITTS commodity codes, which circumvented OCTO’s review. As a result, OCTO did not review and approve approximately $152 million in ITTS requisitions" (OIG Report No. 18-1-19TO). The commodity codes on this site are also chosen when a record is entered, so a filter on them can miss IT purchases too.
  • Software maintenance can skip competition. The law exempts "Maintenance and support of existing software and technology to the extent that the creator of the intellectual property is still protected and is the only source" (§ 2-354.13(8)), and the regulation says this "applies to renewal of existing software licenses purchased either directly from the creator or from an authorized dealer" (27 DCMR § 1703.6).

When the Council must approve a contract

Under the Home Rule Act, a contract involving more than $1,000,000 in spending during a 12-month period can't be made unless the Mayor sends it to the Council and the Council approves it.

Exact wording: D.C. Code § 1-204.51(b)(1)
"No contract involving expenditures in excess of $1,000,000 during a 12-month period may be made unless the Mayor submits the contract to the Council for its approval and the Council approves the contract" D.C. Code § 1-204.51(b)(1) (Home Rule Act)
  • Over $1 million in any 12 months: approved automatically if no Councilmember introduces a resolution within 10 days of the Council receiving it, or if one is introduced and the Council doesn't disapprove within 45 days (§ 2-352.02(b)(2)).
  • Multiyear contracts (a single contract longer than 12 months paid from annual money) work the other way: the Council has to vote yes within 45 days or the contract is "deemed disapproved" (§ 1-204.51(c)(3)). Without approval, a contract "shall not be entered into for periods which extend beyond 12 months" (§ 2-355.04(a)).
  • Over 5 years on multi-year money takes a two-thirds Council vote (§ 1-204.51(a)).
  • Option years count again. Approval of the base contract "shall not constitute Council approval of the exercise of the option", so each option year over the threshold goes back to the Council (§ 2-352.02(b)(3)(B)).
  • The submission must give the contract type, the source selection method, the amount for the base and each option period, and, for a sole-source award, "a detailed explanation of why a competitive procurement is not feasible" (§ 2-352.02(c)).
  • A contractor who knowingly works on a $1 million-plus contract without approval can't be paid more than $1 million, and staff who sign one face discipline (§ 2-352.02(f)–(g)).

How a contract gets awarded

The law lists the allowed methods (§ 2-354.01(a)(1)). Sole-source, emergency and special pilot awards need a written determination and findings (D&F): "a form of written approval and detailed explanation as a prerequisite to taking certain contract actions" (§ 2-351.04(28)).

MethodWhen it's usedKey rulesSource
Competitive sealed bids (Invitation for Bids)The default over $100,000 "Contracts exceeding $100,000 shall be awarded by competitive sealed bidding unless the CPO issues a determination and findings" otherwise. At least 14 days' public notice. The bid invitation says whether award goes on lowest price or lowest evaluated price. § 2-354.02
Competitive sealed proposals (Request for Proposals)When sealed bidding is "not practicable or not advantageous" At least 21 days' notice. Must weigh price, quality and past performance. Negotiation allowed. § 2-354.03
Small purchaseUp to $100,000 No quotes needed at $10,000 or less; at least three written quotes above that. Purchases may not be "parceled, split, divided" to stay under $100,000. § 2-354.07; 27 DCMR § 1800
Sole source"only one source for the required good or service" D&F; notice posted at least 10 days before award; contract online within 7 days. Can't be justified by "lack of adequate advance planning" or "Pending expiration of budget authority". § 2-354.04; 27 DCMR § 1700
Emergency"imminent threat to the public health, welfare, property, or safety" or "serious disruption in agency operations" No longer than 90 days (120 if the thing takes longer to develop). D&F; notice within 7 days. Can't be stretched to expand scope or time except to bridge to a regular contract. § 2-354.05; 27 DCMR § 1702
Exempt from competitionA list set by law Includes software maintenance from the only source, items "federal or District law prescribes" a vendor for, copyrighted material bought from the owner, and services from another public body. § 2-354.13
Special pilot"an unusual or unique situation", including to "Obtain a new technology" Prior public notice, "as much competition as is practicable", D&F posted within 7 days. § 2-354.08
Cooperative purchasingBuying with or through another government Needs the CPO's authorization. § 2-354.11
GSA scheduleBuying off a federal GSA schedule The CPO must make sure the price is reasonable. § 2-354.10
DC Supply Schedule (DCSS)Contracts with certified business enterprises A District schedule "under which contracts may be awarded to certified business enterprises". § 2-354.12
Human care agreementHealth, education and social services delivered to individuals Providers qualify through a request for qualifications; the agreement is "not a commitment to purchase any quantity". § 2-354.06

The law also lists reverse auctions and infrastructure methods, not covered here. The CPO must "publish annually on the Internet a report on the number of and dollar value of contracts executed under each source selection method" (§ 2-354.01(a)(2)). The portal's "market type" field does not record the method reliably; see the column note on the contracts page.

Options, extensions and letter contracts

  • Option: "a unilateral right in a contract under which, for a specified time, the District may elect to extend the term of a contract" (27 DCMR § 2099). On this site each option period is its own row.
  • Limits. The base period "shall not exceed one (1) year" unless paid from multi-year money or a multiyear contract, and base plus options "shall not exceed five (5) years" unless the CPO decides otherwise in writing. To go past the contract's last option, the CPO must find it in the District's interest and the contracting officer must justify "a sole source modification" (27 DCMR § 2005.2). An option can't be exercised "after the contract term has expired" (§ 2005.1).
  • Letter contract: "a written preliminary contractual instrument that authorizes the contractor to begin immediately [...] prior to the execution of a definitive contract" (§ 2-351.04(39)). Allowed when work must start now and a full contract can't be signed in time. The full contract must follow within 120 days or before half the work is done, whichever is first, and the District's liability is capped at 50% of the price ceiling (27 DCMR § 2425, as amended effective 15 May 2026).
  • Modification means "any written alteration in the specifications, delivery point, rate of delivery, contract period, price, quantity, or other contract provisions"; a change order is one the contracting officer can order "without the consent of the contractor" (§ 2-351.04(15), (9)).

Small and local business rules

A certified business enterprise (CBE) is a local business certified by the Department of Small and Local Business Development (DSLBD) (§ 2-218.02). A small business enterprise (SBE) must also be a local business enterprise and meet a size test (§ 2-218.32).

  • $250,000 or less: set aside. "each agency shall set aside contracts or procurements of $250,000 or less for qualified small business enterprises." If the agency finds in writing that there aren't at least two qualified SBEs, any CBE can fill it. The agency can go to the open market if the set-aside bids are "12% or more above the likely price on the open market" (§ 2-218.44; the same rule for the DC Supply Schedule is § 2-218.45).
  • Follow-on work stays set aside. When an SBE or CBE wins a contract, "its follow-on or renewable acquisition shall be set aside" unless DSLBD's Director approves a waiver in writing (§ 2-218.45a).
  • Over $250,000: subcontract 35%. Contracts over $250,000 must have "At least 35% of the dollar volume of the contract [...] subcontracted to small business enterprises" (or CBEs, if there aren't enough SBEs), unless waived. A CBE that wins as the prime must do at least 35% of the work itself (§ 2-218.46(a), (b); this section carries temporary amendments that expire 27 March 2027, which don't change these figures). An option or extension on a contract out of compliance "shall be void" (§ 2-218.46(f)).
  • Preferences in open competition. CBEs get extra points on proposals or a price reduction on bids, capped at "12 points or a reduction in price of more than 12 percent" (§ 2-218.43).
  • Agency goal: 50% of each agency's "expendable budget" to SBEs each year (§ 2-218.41(a)).

"Set Aside" is a value in the portal's market type field, typed by the District (a few periods spell it "Set-Aside"). Both spellings are shown on the contracts page as entered and not checked against these rules.

Contract types

The contract type says how the price works. The law lets the District use "any type of contract which will promote the best interests of the District", within limits (§ 2-355.03), and bans one outright: "An agency shall not enter into a cost-plus-a-percentage-of-cost contract" (§ 2-355.01). Definitions below are from 27 DCMR § 2499 unless another source is given. Each name links to the contracts with that value in the portal's contract type field.

Type (as the portal spells it)What it meansWho carries the cost risk
Firm Fixed Price A set price "not subject to any adjustment on the basis of the contractor's cost experience". To be used "when the risk involved is minimal" (§ 2402.2). The contractor: it "places maximum risk and full responsibility for all costs and resulting profit or loss upon the contractor".
Fixed Price with Economic Price Adjustment A fixed price that moves "upward and downward" on events "specifically defined in the contract", such as published price or labor-cost changes. Mostly the contractor; the District takes the defined price swings.
Fixed Price Incentive Profit goes up or down by formula as final cost lands under or over a target, up to a price ceiling. Shared up to the ceiling; over it, "the contractor will absorb the difference as a loss" (§ 2408.2).
Indefinite Delivery Indefinite Quantity Orders placed as needed, between a stated minimum and maximum. The regulation calls it an "indefinite-quantity contract": it "requires the District to order and the contractor to furnish at least a stated minimum" (§ 2416.8–2416.9). This type fixes how much can be bought, not how it is priced. Past the minimum, the amount on the portal is a ceiling, not a commitment to spend it.
Requirements Covers "all actual purchase requirements of designated District agencies" for an item over a period; quantities are estimates and money is obligated order by order (§ 2416.4, 2416.7). As for indefinite quantity.
Time And Materials Pays "direct labor hours at specified fixed hourly rates" plus materials at cost. Only allowed when costs can't be estimated and the contracting officer finds in writing "that no other type of contract is suitable" (§ 2420.1). The District pays for every hour worked, up to a ceiling "that the contractor exceeds at its own risk" (§ 2420.2).
Labor Hour "a variant of the time-and-materials contract differing only in that materials are not supplied by the contractor." As for time and materials.
Cost Plus Fixed Fee A cost-reimbursement contract with "payment of a fixed fee" that "does not vary with actual cost". The District. Cost-reimbursement contracts pay "allowable costs incurred" up to a ceiling, and may be used only when costs can't be estimated well enough for a fixed price (§ 2405.1), backed by a D&F that it is cheaper or the only practical way (§ 2-355.02).
Cost Plus Incentive Fee Costs plus a fee "adjusted later by a formula based on the relationship of total allowable costs to total target costs". The District, as for Cost Plus Fixed Fee.
Cost Plus Award Fee Contract Costs plus a base fee and an extra fee awarded on "a judgmental evaluation by the contracting officer". The District, as for Cost Plus Fixed Fee.
Letter Contract A preliminary agreement; see above. The District's liability under the letter contract is capped at 50% of the price ceiling.

The type is whatever the District entered on each contract's portal page. A contract's type here is not checked against its paperwork.

The "Of interest" badges on this site

The contracts page marks a few contracts whose posted paperwork shows they weren't bid out the usual way. These are read by hand from the documents and recorded in of_interest.yaml. They are not findings of wrongdoing. We read the paperwork only for current contracts whose attached file names mention a sole source, emergency, letter contract or extension, or whose record looked unusual, so a contract with no badge may simply not have been read. Each badge links to the contracts that carry it.

BadgeWhat it means under the lawSource
Sole source Awarded without competition because "there is only one source for the required good or service". Needs a D&F and a public notice 10 days before award. § 2-354.04
Sole-source extension past the last option Extended beyond the total term the contract allowed. The rule requires a written finding by the CPO and a justification "for using a sole source modification". 27 DCMR § 2005.2(b); § 2-354.04
Exempt from competition A purchase on the statute's list of exemptions, such as software support from its only source or a vendor that "federal or District law prescribes". § 2-354.13
Emergency procurement Bought under emergency procedures for a threat to health or safety or a serious disruption. Limited to 90 days (120 in some cases). § 2-354.05
Letter contract Work started under a preliminary agreement before the full contract was signed. 27 DCMR § 2425
Special pilot procurement Awarded without sealed bids or proposals because of "an unusual or unique situation", which can include obtaining "a new technology". § 2-354.08
Rider or cooperative purchase Bought through a contract another government or agency already had, rather than a new competition. The law calls this cooperative purchasing, which the CPO must authorize. "Rider" covers the case where the paperwork instead cites a rider clause (in one contract here, the "Metropolitan Washington Council of Governments Rider Clause") to order off another agency's existing contract. The statute does not define "rider". § 2-354.11
Grew or slipped after award After a non-competitive award, the paperwork shows the contract grew a lot or its delivery moved out a long way. This is a description, not a legal category; changes like these are made by contract modification or change order. § 2-351.04(9), (15)

What the portal has to publish

The CPO must run a public procurement website (§ 2-361.04). At a minimum it must include:

  • The statutes and rules that govern procurement, "including those exempt from the authority of the CPO".
  • Links to every District website with active solicitations over $100,000.
  • A database of every contract of $100,000 or more, "including each such contract made by a District agency exempt from the authority of the CPO", with a unique identifier, "A copy of the executed contract", "All determinations and findings", "All contract modifications, change orders, or amendments", the solicitation documents, the summary sent to the Council, and whether the vendor is a "covered contractor" under the campaign-finance rules.
  • For contracts under $100,000, a list with "the vendor name, a description of the goods or services purchased, and the dollar amount of the contract".

Agencies outside the CPO's authority "shall transmit the information required by this section to the CPO for posting" (§ 2-361.04(c)). Separate posting deadlines apply to sole-source awards (contract online within 7 days, § 2-354.04(d)) and emergency awards (notice with D&F and contract within 7 days, § 2-354.05(f)).

This page says what the law requires, not whether the portal meets it. For what the portal holds, as we pulled it, see About this data.

Glossary

CBE
Certified business enterprise: a local business certified by DSLBD (§ 2-218.02). See small and local business rules.
Change order
A change the contracting officer can order under the contract's changes clause "without the consent of the contractor" (§ 2-351.04(9)).
Contracting officer
"the Mayor, the CPO, or the CPO’s designee vested with the authority to execute contracts on behalf of the District" (§ 2-351.04(16)).
CPO
Chief Procurement Officer, "the director of the Office of Contracting and Procurement" (§ 2-351.04(11)).
D&F
Determination and findings: the written justification required for a sole-source, emergency, pilot or cost-reimbursement award, among others (§ 2-351.04(28)).
DCMR
District of Columbia Municipal Regulations. Title 27 holds the procurement rules (OCP, Laws & Regulations).
DCSS
District of Columbia Supply Schedule, the District's schedule of contracts with CBEs (§ 2-354.12).
Definitive contract
The full contract that replaces a letter contract (§ 2-351.04(22)).
DSLBD
Department of Small and Local Business Development, which certifies CBEs (§ 2-218.02(3)).
IFB
Invitation for Bids: the solicitation for competitive sealed bids (§ 2-351.04(38)).
Multiyear contract
"a contract for a period longer than twelve (12) months that is funded by annual appropriations" (27 DCMR § 2099). Needs Council approval.
OCP
Office of Contracting and Procurement (§ 2-352.01).
OCTO
Office of the Chief Technology Officer (§ 1-1401). Reviews agencies' IT purchases over $25,000 (1 DCMR § 5602).
Option period
An extra period the District may add at its choice under the contract's terms (27 DCMR § 2099). Listed as its own row on this site.
PPRA
Procurement Practices Reform Act of 2010, D.C. Code § 2-351.01 and following.
RFP
Request for Proposals: the solicitation for competitive sealed proposals (§ 2-351.04(52)).
RFQ
Request for Qualifications: asks for vendors' qualifications only (§ 2-351.04(53)). DC's solicitation list also uses RFQ for a request for quotations, and that is the more common meaning there: titles that spell it out say quotation or quote about three times as often as qualifications.
SBE
Small business enterprise: a local business enterprise that also meets a size test (§ 2-218.32).
Sole source
"a single source in a competitive marketplace can fulfill the specifications of a contract" (§ 2-351.04(59)).